The
building project is 75% complete. The
ambulance road along the fields is done.
They are working on the last of curbing and asphalting for this
fall. Fields will be treated for erosion
control. Signs throughout the parking
lot and site will go up soon, and streetlights will soon be activated. Ninety percent of work being done at this
point is inside the building. The 3rd
floor will be complete by thanksgiving, and the 2nd floor by the holidays. Gym flooring installation will begin the
Monday after Thanksgiving. Metal
paneling and masonry are almost done. Almost
all exterior doors and windows are in. |