Construction Update

posted Dec 7, 2011 8:35 AM by Dianne Estes
The building project is 75% complete.  The ambulance road along the fields is done.  They are working on the last of curbing and asphalting for this fall.  Fields will be treated for erosion control.  Signs throughout the parking lot and site will go up soon, and streetlights will soon be activated.  Ninety percent of work being done at this point is inside the building.  The 3rd floor will be complete by thanksgiving, and the 2nd floor by the holidays.  Gym flooring installation will begin the Monday after Thanksgiving.  Metal paneling and masonry are almost done.  Almost all exterior doors and windows are in.